Language selection

Pipeline Investigation Report P14H0011

Natural gas pipeline rupture
TransCanada PipeLines Limited
Line 400-1 at Mainline Valve Site 402
Near Otterburne, Manitoba

The Transportation Safety Board of Canada (TSB) investigated this occurrence for the purpose of advancing transportation safety. It is not the function of the Board to assign fault or determine civil or criminal liability. This report is not created for use in the context of legal, disciplinary or other proceedings. See Ownership and use of content.

Summary

At approximately 0115 Central Standard Time on 25 January 2014, a natural gas pipeline rupture and ignition occurred on TransCanada PipeLines Limited’s 762 mm (30-inch) Line 400-1 at the site of Mainline Valve 402 near Otterburne, Manitoba. A crater measuring approximately 24 metres long by 12.5 metres wide was created, and debris was ejected approximately 100 metres from the rupture site. Natural gas burned for approximately 12 hours. Five residences in the immediate vicinity were evacuated, and Provincial Highway 303 was closed until the fire was extinguished. There were no injuries.

Factual information

At approximately 0115 Central Standard Time on 25 January 2014, a natural gas pipeline rupture and ignition occurred on TransCanada PipeLines Limited's 762 mm (30-inch) Line 400-1 at mainline valve site 402 near Otterburne, Manitoba. A crater measuring approximately 24 metres long by 12.5 metres wide was created, and debris was ejected approximately 100 metres from the rupture site.

Prior to the occurrence, the TransCanada PipeLines Limited (TransCanada) Mainline system had been operating normally. The operating pressure of the pipeline system at the occurrence site was about 6330 kilopascals (kPa), based on the daily average supervisory control and data acquisition (SCADA) data. For this section of the TransCanada system, the maximum operating pressure (MOP), as approved by the National Energy Board (NEB), was 7030 kPa. Due to lack of customer demand, gas had not been flowing since 5 January 2014 in pipeline 400-1. However, static pressurized gas was present in the line between closed valves.

The occurrence site is located on TransCanada's Line 400-1, at Mainline Valve (MLV) 402, approximately 50 km south of Winnipeg, Manitoba. It is surrounded by agricultural land, with a flat topography. The area is sparsely populated with the nearest dwelling approximately 540 metres to the east. The closest roadway is Provincial Highway 303, located approximately 75 metres to the south. Otterburne, Manitoba, the nearest town, has a population of about 120 residents (Figure 1).

Figure 1. Occurrence site (Source: Google Earth with TSB annotations)
Map of occurrence site

After the initial failure and fire, natural gas burned for approximately 12 hours at the occurrence site. Residents of 5 homes in the immediate vicinity were evacuated until the fire self-extinguished. As a precaution, two adjacent pipelines, lines 400-2 and 400-3, were shut down, assessed, and returned to service on 26 January 2015. This resulted in the loss of natural gas service to 9 rural communities in Manitoba for approximately 80 hours.

The emergency measures implemented by TransCanada included the trucking of compressed natural gas to local hospitals and emergency shelters. Normal gas delivery to affected communities resumed on 28 January 2014 after initial repairs were completed.

At the time of the occurrence, the temperature was −26 °C with calm winds out of the north. Southern Manitoba was experiencing extreme cold-weather conditions that winter, one of the coldest winters since 1898.

TransCanada's pipeline system

TransCanada's Canadian Mainline natural gas pipeline system extends from the Alberta–Saskatchewan border to the Quebec–Vermont border and consists of 57 compressor stations and more than 14 000 km of underground large-diameter pipe. The system, which is composed of up to 8 parallel pipelines, is divided into approximately 30-km intervals by mainline isolation valves.

Line 400 consists of 3 parallel pipelines extending south from Compressor Station 41 on TransCanada's Mainline near Winnipeg, Manitoba, to the export/import point at Emerson, Manitoba. Line 400-1, a 30-inch diameter pipeline, was constructed in 1960; Line 400-2, a 36-inch diameter pipeline, was constructed in 1969; and Line 400-3, a 48-inch diameter pipeline, was constructed in 1990. These 3 pipelines supply natural gas to various customers along the route and also interconnect with Viking Gas Transmission and Great Lakes Gas Transmission at the Canada–USA border.

Although there are no compression facilities on Line 400, there are 5 MLV sites along the pipeline. The MLV sites house the mainline isolation valves, crossover valves, associated piping, and controls. Gas can flow in either direction (north to south or south to north) in each of the 3 pipelines, depending on the configuration of the system.

At the time of the occurrence,

Line 400-1 was designed in 1960 to the American Standards Association (ASA) B31.1.8 code. The 762 mm (30-inch) external diameter pipeline with nominal wall thickness of 9.5 mm was originally coated with coal tar enamel. It was constructed with American Petroleum Institute (API) Grade 52 mild carbon steel pipe, which has a specified minimum yield strength (SMYS) of 359 megapascals (MPa). At the time of construction, there was no requirement to perform radiographic examination of every pipeline weld, nor was there a requirement to retain weld inspection and test records.

Testing and inspection of Line 400-1

Line 400-1 had been hydrostatically tested when the pipeline was originally commissioned in 1960. No other pressure test had been performed on Line 400-1 since then. Welding and non-destructive examination records from the commissioning of Line 400-1 had not been retained.

Internal inspections of Line 400-1 had been performed as follows:

In the vicinity of the occurrence, integrity-related activities had been performed as follows:

Following the 1999 excavations, a 38-metre section of pipe located upstream of MLV 402 on Line 400-1 was cut out and replaced due to the presence of SCC.

Design and construction of the MLV 402 site

The MLV 402 site was designed and built in 1960 as part of the construction of Line 400-1. Line 400-2 was constructed in 1969, and was tied over to Line 400-1 at MLV 402 and MLV 403 in 1979. The original 1960 design and as-built drawings of the MLV 402 site could not be located. However, since the MLV 402 site is of the same design as the MLV 403 site, the as-built drawings of the MLV 403 site were examined and compared with the current configurations of both MLV sites.Footnote 5 No inconsistencies with respect to valve supports were identified.

Over the years, multiple excavations and backfill activities had occurred in the vicinity of the MLV 402 site as part of normal facility repair, maintenance, and upgrade. The most recent maintenance activity at this location was in early January 2014, for gas handling operations, which involved snow removal to gain access to the valve site.

Site examination

A detailed site examination was performed after the occurrence, and the following was determined:

Figure 2. Lines 400-1 and 400-2 and associated piping and valves in the vicinity of the failure at the MLV 402
Diagram of lines 400-1 and 400-2 and associated piping and valves in the vicinity of the failure at the MLV 402
Photo 1. Pipeline failure damage
Photo of the pipeline failure damage

Laboratory analysis of the failed pipe

The failed sections of pipe (approximately 14.36 metres)—including MLV 402-1—were cut out and transported to TransCanada's compressor station 41 in Ile-des-Chênes, Manitoba. After initial examination, the pipe components were shipped to the Acuren Group Inc. (Acuren) laboratory in Edmonton, Alberta, for metallurgical analysis.

The analysis included visual examination, photography, magnetic particle inspection, radiography, metallography, scanning electron microscopy, mechanical testing, and chemical analysis, and the following was determined:

Photo 2. Pre-existing crack at girth weld
Photo showing pre-existing crack at girth weld

Regulatory requirements for pipeline integrity management

Section 40 of the NEB Onshore Pipeline Regulations, 1999 (OPR) requires a company to develop a pipeline integrity management program. While the OPR does not prescribe the integration of all industry standards or best practices into pipeline integrity management programs, it requires companies, through incorporation by reference in subsection 4(1), to adhere to mandatory Canadian Standards Association (CSA) Z662Footnote 8 requirements.

While the NEB, in its Guidance Notes for the Onshore Pipeline Regulations, 1999, provides some direction in developing a pipeline integrity management program, regulated companies have flexibility and discretion to develop the content of their pipeline integrity management program. Therefore, companies develop pipeline integrity management programs tailored to their specific circumstances, and will initiate corrective action for defects which are known to exist or are found to exceed criteria set in CSA Z662.

The effectiveness of each regulated company's program is monitored by the NEB on an ongoing basis, with the goal of ensuring that pipelines are suitable for continued safe, reliable, and environmentally responsible service.

TransCanada's integrity management program

TransCanada's integrity management program (IMP) is the governing document the company uses for managing the integrity of its pipeline facilities. The IMP uses a risk‑based pipeline integrity management process. It is based on various standards such as CSA Z662 (as required by the regulatory provisions) as well as various other industry standards and recommended practices, such as certain annexes to CSA Z662, and relevant codes and/or standards of the American Society for Mechanical Engineers, the American Petroleum Institute, and the National Association of Corrosion Engineers.

One of the core components of the IMP is the management of the safety and reliability of line pipe and other facilities. The IMP includes continuous monitoring of all the operation and maintenance aspects of line pipe and other facilities. Identified or observed deficiencies are escalated as necessary in accordance with TransCanada's written procedures so that every identified situation is addressed.

Manufacturing defects are one of the system-integrity threats identified in the IMP. TransCanada's approach to quantifying and mitigating such threats includes the use of engineering critical assessments, in-line inspections, and investigative digs, in conjunction with non-destructive examinations.

Analysis

The accident

Line 400-1 ruptured approximately 1 metre north of MLV 402-1 due to a circumferential brittle fracture that initiated at a pre-existing crack. The pre-existing crack was a delayed hydrogen crack located in the hard heat-affected zone of the circumferential transition weld between a bypass tee and a short section of adjacent pipe. This crack had been formed at the time of the pipeline's construction, likely due to an inadequate welding procedure and poor welding quality. The weld defect had remained stable for over 50 years prior to the failure and there was no indication that it had grown in service. Due to internal pipe pressure and forces in reaction to the failure, MLV 402-1 and an 11 metre–long section of pipe to the south were lifted up during the failure. This resulted in a sharp wrinkle at a girth weld at the top of the pipe, causing a secondary failure. The natural gas released from the pipeline ignited, and the resulting fire burned for approximately 12 hours.

The weld at the initial failure point would have been performed manually at the valve fabrication shop, as was the practice at the time of construction. The welding would likely have been completed with welding consumables and practices in place at that time. The strength of these welds would likely have matched the grade of the pipe and fittings.

The original standard for the pipeline's construction, ASA B31.1.8, did not require every weld to be inspected using radiography. Furthermore, as the standard had no requirement for the retention of weld inspection and test records, no such records were retained. Based on standard industry practice at the time of construction, the weld at the failure location had likely been inspected only by visual means.

The source of the incremental stresses that caused the fracture could not be determined with certainty. It is likely that one or more sources of secondary loading stresses were present at the valve assembly. Possible sources include

Testing and inspection of Line 400-1

The segment of Line 400-1 that failed was hydrostatically tested when the pipeline was originally commissioned in 1960. No other pressure test had been performed on Line 400-1 since that time.

The integrity management program (IMP) in effect for Line 400-1 at the time of the occurrence included the management of integrity threats due to possible manufacturing and construction defects. The IMP included the use of in-line inspection in conjunction with targeted integrity excavations. In 2001 and 2009, Line 400-1 was internally inspected using caliper and high-resolution magnetic flux leakage tools. Since 1997, 36 integrity excavations involving non-destructive examinations of exposed pipe surfaces had also been performed at selected locations. These activities identified areas of external corrosion and stress corrosion cracking, which were subsequently repaired. TransCanada's IMP also relied on an engineering assessment to evaluate integrity threats due to manufacturing defects on this pipeline, and determine its fitness for service. If integrity threats due to manufacturing defects, especially in older pipelines, are not identified, pipeline integrity may be compromised, increasing the risk of in-service failures.

Findings

Findings as to cause and contributing factors

  1. Line 400-1 failed due to a circumferential brittle fracture that initiated at a pre-existing crack that had remained stable for over 50 years prior to the occurrence.
  2. The crack had formed at the time of the pipeline's construction, likely due to an inadequate welding procedure and poor welding quality.
  3. During the failure, MLV 402-1 and an 11 metre–long section of pipe to the south lifted up, resulting in a sharp wrinkle at a girth weld at the top of the pipe, causing a secondary break.
  4. Soil support in the vicinity of the MLV 402 site may have been weakened due to multiple excavations and backfill activities over the years as part of normal facility repair and maintenance.
  5. Frost in the ground was likely deeper than normal due to the record cold winter in southern Manitoba.
  6. Maintenance work in January 2014 at and around the MLV 402 site may have driven frost even deeper into the ground.
  7. Secondary loading of the valve assembly with respect to the pipe may have occurred, increasing the stresses at the failure location.
  8. Thermal contraction may have occurred when the pipeline cooled due to the absence of gas flow for 20 days.

Findings as to risk

  1. If integrity threats due to manufacturing defects, especially in older pipelines, are not identified, pipeline integrity may be compromised, increasing the risk of in-service failures.

Other findings

  1. The pipeline's original construction standard did not require the inspection of every weld using radiography, and the weld at the failure location had likely been inspected only by visual means.
  2. The pipeline's original construction standard had no requirement for the retention of weld inspection and test records, and no such records were likely retained.

Safety action

Safety action taken

National Energy Board

Following the occurrence, the following safety actions were taken by the National Energy Board:

  1. TransCanada was required to submit an engineering assessment demonstrating that Line 400-3 was fit for service prior to returning the pipeline to service on 26 January 2014.
  2. TransCanada was required to investigate all remaining valve sites along Line 400-1 to determine the existence of valve assemblies similar to that in the incident.
  3. TransCanada was required to submit an engineering assessment demonstrating the fitness for service of Line 400-1 prior to its return to service.
  4. TransCanada was required to undertake a review of its valve installations to evaluate whether similar valve assemblies exist throughout its system.

TransCanada

Following the occurrence, the following safety actions were taken by TransCanada:

  1. In February 2014, a ground-based leak detection was completed 500 metres upstream and downstream of the occurrence location. No leaks were detected.
  2. A program was initiated to excavate, inspect and, where applicable, repair all of the mainline valve assemblies on Line 400-1. The program included
    • confirmation of the presence of supports as per design drawings;
    • inspection of all the girth welds in the vicinity of the valve assemblies to ensure their integrity, using magnetic particle inspection, radiography and ultrasonic inspection;
    • performance of hardness testing on all flash butt-welded pups that are part of the original valve assemblies; and
    • repair of defects exceeding the acceptance criteria outlined in CSA Z662.
  3. In October 2014, an engineering assessment was prepared by TransCanada to demonstrate safe operation of the pipeline at a reduced pressure; the assessment was submitted to the National Energy Board.
  4. Following the return to service of Line 400-1, TransCanada performed magnetic flux leakage and electromagnetic acoustic transducer  in-line inspections of the pipeline to rule out other threats to safe operation.
  5. In 2014, various cathodic protection upgrades were performed, and a complete close-interval survey of the cathodic protection system on the entire Line 400 was completed.

This report concludes the Transportation Safety Board's investigation into this occurrence. The Board authorized the release of this report on 10 June 2015. It was officially released on 28 July 2015.